• Project Time Control In Building Construction

  • CHAPTER ONE -- [Total Page(s) 3]

    Page 2 of 3

    Previous   1 2 3    Next
    • In order to establish a basis from which to calculate a schedule using the duration estimates for the activities, it’s necessary to select the estimated start time and required completion time for overall project. These times define overall window or envelope, of time in which the project must be completed. The projects required completion time is normally part of the project objective and stated in the contract. Once the, estimated duration for each activity in the network and an overall window of time in which the project must be completed, you have to decide whether the activities can be done by the required completion time.
      The key to effective project time control is to measure actual progress and compare it to planned progress on a timely and regular basis and to take necessary corrective action immediately. The project time control process involves regularly gathering data on project performance, comparing with the planned performance. This process must occur regularly throughout the project.
      It starts with establishing a baseline plan that shows how the project scope will be accomplished on time and within the budget. Once this baseline plan is agreed with the customer the project starts. A regular reporting period should be established for comparing the actual progress with the planned progress. Reporting may be daily, weekly, or monthly depending on the complexity and the duration of the project. During each reporting period, two kinds of data or information need to be collected.
      1.2 STATEMENT OF PROBLEMS
      Ackermann, Eden, Howick and Williams (2000) point out the pitfall of using 0. They are:
      a) When a network is resource-constrained, there is no agreed definition of what a 'project time control ' actually is.
      b) Many effects, such as change orders, impact many activities simultaneously. In such cases, single-activity analyses in PRC do not really work, and more sophisticated analyses or network simulation is needed.
      c) PRC cannot take account of soft factors such as demotivation. Disruption affects productivity in a fashion that means it varies over time, PRC times do not usually take account of changes in productivity, let alone when it is a variable factor.
      d) project time control (PRC) does not take into account management actions to deal with delays and disruptions.
      Adding resource
      Adding resource is most common methods for shortened project time. But there are limits, such as some of activities cannot be shortened by adding staffs and equipment and some time the relation between staffs size and time shorten is not linear. Adding resource, you cannot achieve as your want.
      Overtime
      This is the easiest way to add more labour and not add more staffs. But need to face the challenge of team numbers' antipathy and the low efficiency in the overtime work.
      Outsourcing
      This is also a common method to shortening the project time by subcontracting the activities. The issue is most of the time, the subcontractor need to warm up before start their project jobs.
      NPV
      The problem that exists within the field of NPV is that after getting a project authorized.
      There will be no further consideration given to the project's NPV until a post investment appraisal can be carried out. However, at this point the damage has been done (Gardiner and Stewart, 2000, p252).
      1.3 OBJECTIVE OF THE STUDY
      Erel and Raz (2000) state that the project time control cycle consists of measuring the status of the project, comparing to the plan, analysis of the deviations, and implementing any appropriate corrective actions. When a project reach the construction phase, monitor and control is critical to deliver the project success. Project monitoring exists to establish the need to take corrective action, whilst there is still time to take action. Through monitoring the activities, the project team can analyze the deviations and decide what to do and actually do it (Gardiner and Stewart 2000,p252). The purpose of monitor and control is to support the implementation of corrective actions, ensure projects stay on target or get project back on target once it has gone off target (Erel and Raz, 2000,p253).
      a) Do unstarted activities really have to await the completion of other activities before they can start? If no, start the activities
      b) If an activity has to wait for the completion of other activities, can that activity be broken down into sub-activities and some of the sub activities completed at an earlier date? If no, break down the activity into sub-activities and start the urgent one at once.
      Herroelen and Reyck (1999) also state that managers have to tackle the challenging problem of scheduling activities to minimize the project duration, in which the activities (a) are subject to generalized precedence relations, (b) require units of multiple renewable, non-renewable and doubly constrained resources for which a limited availability is imposed, and (c) can be performed in one of several different ways, refected in multiple activity scenarios or modes.

  • CHAPTER ONE -- [Total Page(s) 3]

    Page 2 of 3

    Previous   1 2 3    Next