• Effective Safety And Health Planning On Construction Sites
    [ONITSHA AND AWKA OF ANAMBRA STATE]

  • CHAPTER TWO -- [Total Page(s) 10]

    Page 1 of 10

    1 2 3 4 5    Next
    • CHAPTER TWO
      2.0. LITERATURE REVIEW
      2.1    FORMS OF PROJECT PLANNING
      Planning naturally precedes execution of any worthwhile venture. It is the correctness of the details of the planning and their effective implementation by those concerned that determine the success or failure of that venture.
      2.1.1    Butler (1979) writing on the essence of planning stated that: “planning aims to lay down the direction in which a move is made forward, taking into account the resources that are available; that nothing can result without a plan in any form of production as activities will not be related and persons will go their own ways- the result: chaos and disorder.”
      He listed the following forms of planning:
      I.    Policy planning
      II.    Pre-tender planning
      III.    Pre-contract planning
      IV.    Short-term planning
      V.    Weekly planning
      2.1.1.1    Policy planning: This is the planning    that    states    the    objective, focus and procedure of actions of the firm; these are normally laid down in writing as a guide for official transactions. It also encompasses personnel matters like: training, promotions, retirement/ pension schemes, insurance, safety, injuries / compensation etc.
      2.1.1.2    Pre-Tender planning: Tendering is a process of contact procurement.
      To fully obtain relevant data and organize same for use in the course of tendering, a form of planning is needed and this is called pre-tender planning.
      He stated that the procedure of pre-tender planning needs to be planned so that a systematic approach can be made to ensure that all information and facts are gathered on time. A typical example of this procedure is as follows:
      1.    The pre-tender report (site investigation)
      2.    Method statement
      3.    Plant schedule
      4.    Site organization structure and site on -costs
      5.    Sub-contractors and suppliers
      6.    Outline programme
      7.    Final estimate (for board’s decision)
      •    Pre tender report: - This is a document compiled to show in as comprehensive a form as possible all information regarding the area and general site condition. Apart from lending insight on cost implications, it shows also safety and health implications inherent on the site that should be planned for.
      •    Method statement: - Basically this indicates how the project is to be built, what method and plant to be used. Each stage of the operation is studied to find the best method of completing it, carefully weighing the various alternative methods that could be adopted.
      •    Plant Schedule:- This is carried out on the completion of the method statement and is a detailed summary of all the plant and equipment required to build a project, giving as mush relevant detail as possible to avoid site congestion that makes it chaotic and prone to accidents.
      •    Site organization/outline programme: - These ensure the orderly site arrangement for hutment, material storage and activities procedures in a way that allows for easy flow of engagement.
      2.1.1.3    Pre contract planning: - when a builder is successful in his tender and is asked to undertake the project, upon signing the contract document, he will be allowed a short period of time to make preparation and organize his resources before actual commencement of work. This period of time is called pre-contract period and will vary in time with the size and nature of the project The benefits of sound pre-tender planning will enhance the pre-contract planning activities.
      Major items dealt with at this stage would include:
      1.    Site layout and general organization
      2.    Labour and plant requirement finalized
      3.    Contract programmer prepared
      In engaging with the above listed items attention should be paid to the inter relationship of activities with the view to avoid congestion or situations of conflicts and hasty actions that can lead to bottlenecks and subsequently accident and injuries.

  • CHAPTER TWO -- [Total Page(s) 10]

    Page 1 of 10

    1 2 3 4 5    Next
    • ABSRACT - [ Total Page(s): 1 ]ABSTRACTThe major purpose of this study was how to use good planning of construction activities to achieve safety, good health, control and prevention of accidents on building construction sites.The population of the study consisted mostly of big construction firms in Anambra State, especially Awka and Onitsha that have had more than 5 years of active construction activities. The sample for the study was 10 reputable construction firms; five from Awka and 5 from Onitsha; which were drawn using s ... Continue reading---

         

      TABLE OF CONTENTS - [ Total Page(s): 1 ]TABLE OF CONTENTSPAGETITLE PAGE CERTIFICATION   DEDICATION   ACKNOWLEGEMENTS   TABLE OF CONTENTS    LIST OF TABLES   ABSTRACT   1.0    CHAPTER ONE   1.1    INTRODUCTION   1.2    BACKGROUND OF THE STUDY   1.3    STATEMENT OF THE PROBLEM  1.4    AIM AND OBJECTIVE OF THE STUDY  1.5    SIGNIFICANCE OF THE STUDY    1.6    HYPOTHESES 1.7.1    SCOPE AND DELIMITATION OF THE STUDY  1.7.2    LIMITATIONS OF THE STUDY   1.8    RESEARCH QUESTIONS  1.9 ... Continue reading---

         

      CHAPTER ONE - [ Total Page(s): 2 ]1.4    AIM AND OBJECTIVE OF THE STUDYThe aim of the study is how to use good planning of construction activities to achieve safety, good health, control and prevention of accidents on building construction sites with the following objectives:•    To    identify    health    and    safety    problems    associated    with    building construction industry.•    To find out factors that lead to health and safety problems•    To investigate how t ... Continue reading---

         

      CHAPTER THREE - [ Total Page(s): 2 ]3.0    CHAPTER THREE3.0.1 RESEARCH METHODOLOGY3.1    INTRODUCTIONThis chapter describes the approach adopted in this study as itemized below: i    Design of the studyii    Area of the studyiii    Population of the studyiv    Sample And Sampling Techniques v    Instruments For Data Collectionvi    Validation Of The Instruments vii    Method Of Data Analysis3.1.1    DESIGN OF THE STUDYThe research design adopted for the study was the survey method. The survey inst ... Continue reading---

         

      CHAPTER FOUR - [ Total Page(s): 19 ]Question SixYears of working experience?The data relevant to this question are presented in table 4.4Data presented in table 8 above showed that 4 respondents, which represent 12.5% have 2-5 years working experience. 4 respondents again, which represent 12.5 have 6-10 years working experience. 8 respondents, which represent 25% have 11-15 years working experience and 16 respondents, which represent 50% have 16 years and above working experience.This therefore shows that 24 respondents, which rep ... Continue reading---

         

      CHAPTER FIVE - [ Total Page(s): 3 ]5.1.4    IMPLICATIONS OF THE STUDYThis study on the effective safety and health planning of construction   activities, as a tool for accident prevention and control on sites has a lot of social, construction and economic implications. The results of this research having shown the types of accidents; types of health/safety problems; factors that cause construction health and safety problems; how health and safety problems can be mitigated and how government /professional bodies can play sign ... Continue reading---

         

      REFRENCES - [ Total Page(s): 1 ]REFERENCESACT, (2007). Safety Hand BookACT Building and construction industry Australia.Amaechi, 1.0. (1990).    Accidents on construction sites. The Registered Builders Journal. N10B Publication. Vol.1 No.2/Sept.7-11Bokinni, S.K.(2001).    Health and safety on construction site, technical papers. Quality Assurance And Safety In Construction Industry. N10B Publication. 2-21Butler, J.T.(1979). Elements of Administration for Building Students. 2nd edition. London: Hutchinson and co (Publishe ... Continue reading---