    • 4.0    JUSTIFICATION
          The construction of drainage, canal and culvert in the country is given much of structural or engineering consideration with little or no environmental impact assessment of the operations after the design and construction. The environmental problem results from operation which are usually devastating.
          Hence, this study significantly addresses the following issues.
      •    Identify the environmental hazards associated with the drainage, canal and culvert.
      •    Evaluate the magnitude or significance of the hazard and effect.
      •    Identify changes in downstream hydrology.
      •    Identify changes in downstream morphology caused by altering the flow pattern.
      •    Examine control techniques to eliminates or lesson the severity of the effect and to manage the hazards.
      •    Develops plan and procedures to manage the environmental changes due to the operation of the drainage, canal and culvert.
      5.0    SCOPE OF THE STUDY
          This project focus on the investigation into the causes of blocked drainage, canal and culvert; its effect and the possible control measure within Ilorin-west local government area in Ilorin.
          The investigation covered the basic hazard which may be caused by blocked drainage, canal and culvert to the human environment and to look into the causes in the place it happens within Ilorin-west local government. Investigating the various control measure needed to bring blocked drainage, canal and culvert under control.
      6.0    DESCRIPTION OF THE PROJECT AREA
          Ilorin west is one of the sixteen (16) local government in Kwara state and also one of the five (5) local government that made up Kwara central popularly known as (Emirate) with its headquarters located/ situated in Wara Osin in Ilorin metropolis, this capital of Kwara state. A case study of Agbo-oba, oja-tuntun and Sawmill was assigned.
      7.0    RESEARCH METHODOLOGY
          The methodology employed are:- preliminary data source, which may include:-
      A.    RECONNAISSANCE SURVEYS
      This is the feasibility study of the area to determine the Feeder Rivers, geology of the area and level of deterioration of building causes by flood as a result of blocked drainage, canal and culvert and also investigation into the cause of the blockage and also know the control measure to be used or adopted.
      B.    ORAL INTERVIEW
      Oral interview was conducted to hear the view of the residents on the causes of blocked drainage, canal and culvert and to determine the control measure of the blocked drainage, canal and culvert in other to suggest the best control measures.
      C.    ADMINISTRATION OF QUESTIONNAIRE
      Questionnaires was distributed for analysis      

  • CHAPTER ONE -- [Total Page(s) 2]

    Page 2 of 2

    Previous   1 2
    • ABSRACT - [ Total Page(s): 1 ]ABSTRACTDrainage is an essential component of road construction. In most designs of the road, the first thing to be put in place is drainage system. The presence of blockage in drainage system tends to reduce the carriage capacity of drainage and thereby affect life span of the road. The research employed a research survey in order to obtain the information that would describe the causes of blocked drainage, canal and culvert in Ilorin-west local government road and its effect on the surrounding ... Continue reading---

         

      APPENDIX A - [ Total Page(s): 3 ]APPENDIX ... Continue reading---

         

      LIST OF TABLES - [ Total Page(s): 1 ]LIST OF TABLESTable                               Title                             4.1    Response rate in rate in Agbo-Oba, Oja-Tuntun and Sawmill 4.2    Number of years spent by the respondent rate in Agbo-Oba, Oja-Tuntun and Sawmill  4.3    Possible causes of the blockage in Agbo-Oba, Oja-Tuntun and Sawmill       4.4    Control of blocked drainage, canal and culvert    ... Continue reading---

         

      LIST OF PLATES - [ Total Page(s): 1 ]APPENDIXS (LIST OF PLATES) Plate                     Title                       1.0    Drainage blockage along Agbo-Oba road       2.0    Drainage blockage along Sawmill road     3.0    Drainage blockage along Oja-Tuntun, kuntu area   ... Continue reading---

         

      LIST OF FIGURES - [ Total Page(s): 1 ]LIST OF FIGURESFigure                     Title   4.1     Consideration for hydraulic design      4.2     Years spent by the respondent    4.3     Frequency of road usage by road users   4.4     The possible cause of the blockage   4.5     Control measure in Agbo-Oba, Oja-Tuntun and Sawmill   ... Continue reading---

         

      TABLE OF CONTENTS - [ Total Page(s): 1 ]TABLE OF CONTENTSTitle page    Declaration  Certification  Dedication  Acknowledgement  Abstract  Table of Contents  List of Tables   List of Figures  Appendix (List of plates)   CHAPTER ONE1.0     Introduction  2.0     Statement of the problem   3.0    Aim and objectives  4.0    Justification  5.0    scope of the study  6.0    Description of the project area   7.0    Research methodology  CHAPTER TWO2.0    Literature Review   2.1    Introduction ... Continue reading---

         

      CHAPTER TWO - [ Total Page(s): 6 ]2.3      TYPES OF DEBRIS2.3.1     OverviewBlockages can result from a wide range of materials as outlined in Table 2.1. ... Continue reading---

         

      CHAPTER THREE - [ Total Page(s): 3 ]CHAPTER THREE3.0    METHODOLOGY3.1     INTRODUCTIONThis chapter outlines research design; research techniques adopted in this research; data collection procedures and data analysis and presentation methods. The main aim of this chapter is to outline how this study found answers to the research questions that were derived from the research problem. It looked at the data collection instruments and how those instruments were employed so as to obtain information and therefore achieve the rese ... Continue reading---

         

      CHAPTER FOUR - [ Total Page(s): 8 ]CHAPTER FOUR4.0    DATA PRESENTATION AND ANALYSIS OF RESULT4.1     Introduction This chapter focuses on the presentation and analysis of data obtained from the research observations and questionnaires. The data collected from the respondents and field study was presented in order to achieve the objectives of this research project. 4.2     Results from questionnaires Questionnaires were administered to the engineers in Ilorin west government council and Bitto Nigeria Ltd. Another questi ... Continue reading---

         

      CHAPTER FIVE - [ Total Page(s): 1 ]CHAPTER FIVE5.0    CONCLUSION AND RECOMMENDATION5.1     CONCLUSIONThe level of awareness of waste collection services and waste management regulations were relatively low in Abgo-oba, Oja-tuntun and Sawmil, the percentage of those who use indiscriminate solid waste disposal methods like open dumping, open burning and dumping in drainages, canal and culvert were higher. Educational status, age, gender, cost of waste collection services and the location of resident among others ... Continue reading---

         

      REFRENCES - [ Total Page(s): 1 ]REFERENCES(1.)    Barthelmess, A. and E. Rigby (2009) Quantification of Debris    Potential and Evolution of a Regional Culvert Blockage Model, H2009-32nd Hydrology and Water Resources Symposium, Newcastle NSW,November.(2.)    Blockage during Large Storms, 9th International Conference on Urban Drainage, Portland Oregon, September 2002.(3.)    Boyd,M, E. Rigby, S. Roso, P. Silveri and A. Davis (2002) Causes and    Effects of Culvert.(4.)    Braudrick, C. and Grant, G., 2001. Tra ... Continue reading---