• Solar Power Inverters, Analysis And Test Evaluation

  • CHAPTER ONE -- [Total Page(s) 3]

    Page 3 of 3

    Previous   1 2 3
    • The brands of inverters tested were the famous blue gate inverters and luminous inverter technologies.  The tests carried out were repeated severally to obtain correct values. Basic tests carried out include:
      Variable load test
      Constant load over time
      Idle test
      Night time power consumption
      Generally, all tests were grouped into:
      Test for input characteristics
      Test for output characteristics
      Protection test and other special tests.
      The wave form of both inverters were also observed on an oscilloscope, and comparisons were made and recorded in chapter five (5) of this report. The harmonic distortions were observed but not measured.
      Limitations of the study
      Within the course of this project, certain problems/constraints were encountered. Some of these problems/constraints encountered marginalized the area under study while others prevented the complete carrying out of certain tests/test procedures. Some of these problems include:
      Poor state of equipment; some analogue measuring equipment like the high range ammeter available was improperly damped, making it almost impossible to read instantaneous values of current.
      There was a shortage in the availability of high range measuring equipment at the school lab. This restricted tests carried out to lower values. Certain tests had to be attenuated or completely stopped when the values obtained exceeded the deflection of analogue meters, or the range of digital meters.
      Unavailability of certain measuring equipment like the THD analyzer used in the measurement of harmonic distortion. Computer programs like the PV array simulator, required to carry out MPPT performance test was also not available.
      As a result of shortage in certain measuring equipment, the data collected were from various measuring instrument ( analogue, digital), leading to a non-uniform measurement
      Unavailability of standard connecting cables
      The duration for the study, when compared to the volume of work required for completely carrying out the project was limited.
      We also had inadequate financing as at the instant it was required
  • CHAPTER ONE -- [Total Page(s) 3]

    Page 3 of 3

    Previous   1 2 3