    • In this project,
      Theodolite and Electronic Distance Measurement (Leica TC 600 total station) was used for traversing, and direct linear measurements respectively were used. For profile and cross section leveling, a Levelling Instrument was used.
      3.2.4.3 LEVELING
      Leveling is the process of determining the differences in height between points on the earth surface.
      The following ground methods could be used to determine the relative height of survey points, these are:
      (a)    Spirit leveling
      (b)    Trigonometric leveling
      (c)    Barometric leveling
      The method used in carrying out the relative heighting for this project was the spirit leveling method. This operation started from a known heightened control or benchmark (FSS2/GPS/121) running through both longitudinal and cross sectional points and closed back to another benchmark (FSS2/GPS/03).
      In this project, level Observations were carried out in two ways namely:
      (i)    Longitudinal or profile leveling
      (ii)    Cross section leveling.
      Longitudinal or profile leveling: This is the operation of levels along the centre line of any proposed route such as roads, railway, etc, at regular intervals. The centre line was mark at 30m interval.
      These points were heightened by means of leveling operation using a dumpy leveling and the leveling staff. The back sight was taken before the foresight.  The importance of the profile is to provide information about the difference in height of points along the centre line of the route. 
      Cross section leveling: This is the operation of taken levels perpendicular to the direction of centre line of the route that is, right angle to the longitudinal section.
      Cross section was needed to provide information about the ground character on either side of the longitudinal sections. The importance of this is to show any variation in ground slope on either of the centre line which could have considerable effect on the amount and type of construction work involved if details information about them were not knows. In this project, the cross sections were marked at 7.5m/7.5m offset interval from the centre line .i.e. 15m at both sides from the centre line.
      Leveling started from a bench mark FSS2/GPS/121while the instrument was placed outside the line and observation was made to the bench mark at backsight while other observation were intermediate. During this observation, every change in instrument, the last observation which was the foresight became our backsight.


  • CHAPTER THREE -- [Total Page(s) 9]

    Page 8 of 9

    Previous   4 5 6 7 8 9    Next
    • ABSRACT - [ Total Page(s): 1 ]ABSTRACTTheproject was focused on the execution of route surveying for the purpose of road reconstruction from Oriawo along Ogbomosho road, Oyo to School of Science, Sabo Oyo Town. Stations were selected along the existing route at regular intervals as in the specificationsTheodolite traverse was run over stations, while levels were observed along the longitudinal and cross-sections of the traverse lines. All data were gathered with effective orientation from the controls, these were used to pro ... Continue reading---

         

      APPENDIX A - [ Total Page(s): 1 ]FEDERAL SCHOOL OF SURVEYING, OYO                                                                                                                                    FinalProject On Route Surveying                                                                                        ... Continue reading---

         

      LIST OF TABLES - [ Total Page(s): 1 ]LIST OF TABLESTable 3.1: Coordinates of existing ground controls used Table 3.2 Collimation test Table 3.3: Initial control check observation.  Table 3.4: Back computation of initial control used  Closing control check observation. Back computation of initial control used Table 4.1 Sample of Horizontal angle reduction Table 4.1 Back computation of traverse pegs ... Continue reading---

         

      LIST OF FIGURES - [ Total Page(s): 1 ]LIST OF FIGUREFigure 1.1: Study Area diagram    Error! Bookmark not defined.Figure 3.1 Recce Diagram Figure 3.2: Leveling instrument set up mid-way (first set-up) Figure 3.3: Leveling instrument set up( second set up) Figure 3.4 Initial control check observations  Figure 3.6 A typical monument used Figure 3.7: Longitudinal sections leveling. Figure 3.8: Cross-sectional leveling. Fig.: 3.9 – Illustration of detailing by tachometer method ... Continue reading---

         

      TABLE OF CONTENTS - [ Total Page(s): 1 ]TABLES OF CONTENTSTITLE PAGE CERTIFICATE CERTIFICATION DEDICATION  ACKNOWLEDGEMENTS ABSTRACT  LIST OF FIGURE LIST OF TABLES CHAPTER ONE 1.0 INTRODUCTION 1.1 BACKGROUND TO THE STUDY   1.2 STATEMENT OF PROBLEMS  1.3.0 AIM AND OBJECTIVES OF THE STUDY     1.3.1 AIM    1.3.2 OBJECTIVES  1.5 SCOPE OF THE PROJECT 1.6    PERSONNEL   1.7    STUDY AREA CHAPTER TWO   2.0    LITERATURE REVIEW  RECONNAISSANCE PRELIMINARY SURVEY  LOCATION SURVEY  OFFICE LOCATION: -  CHAPTER THREE ... Continue reading---

         

      CHAPTER ONE - [ Total Page(s): 3 ]CHAPTER ONE1.0 INTRODUCTION1.1 BACKGROUND TO THE STUDYEngineering Surveying is one of the branches of surveying which from the general express for any survey work carried out in connection with construction engineering and building project, it is a large scale topographical map survey which the basis for design of engineering works such as highways, railways, canals, tunnels, dams, pipelines and transmission lines.In the word of engineering and environmental studies, surveying has been recognize ... Continue reading---

         

      CHAPTER TWO - [ Total Page(s): 3 ]Traverse is a sequence of connected straight lines whose direction and distances have been measured. Traverse is also the process of connecting series of lines with known bearings and distances. It is subdivided into first order for precise measurement and second order for the establishment of secondary controls while the third order is meant for survey of tertiary and topographical features.Basak (2000) explained leveling as the art of determining the relative vertical heights of different poin ... Continue reading---

         

      CHAPTER FOUR - [ Total Page(s): 5 ]CHAPTER FOUR4.0      DATA PROCESSING AND RESULT ANALYSIS    This involved calculations that are based on acquired data from the field observation to determine locations, direction, height, distance and area etc. some specific formulae were employed for each data set depending on the desired end products and great degree of precision was required.4.1    FIELD BOOKS REDUCTIONS    Every field book was reduced to generate the final data set to be used in the final computation4.1.1   ... Continue reading---

         

      CHAPTER FIVE - [ Total Page(s): 1 ]CHAPTER FIVE5.0    SUMMARY, RECOMMENDATION AND CONCLUSION5.1     SUMMARYThe reconnaissance, which was the main planning, was carefully carried out because of its importance to good execution of any survey project or work. Having carried out the reconnaissance, six (6) second order control stations were located and used as connection along the given route. The total number of nineteen (19) stations excluding the controls where the angles and distances were determine by a closed traverse met ... Continue reading---

         

      REFRENCES - [ Total Page(s): 1 ]REFERENCESBANNISTER AND RAYMOND (1977) Surveying: 4th Ed, Pitman Publishing Ltd, London. Pg. 205BASAK, N.N (2000): Surveying and leveling, Tata Mchraw Hill publishing company Delhi, p.173, Pp.439-444.BRINKER, R. C. AND MINICK, P. R. (1987): Elementary Surveying, 6th Edition IEP- A     Donnseley New York. Pg. 3CLARK, DAVID (1972): Pane and Geodetic surveying for Engineers, 6th edition, vol.1, London: Constable and Co. Limited, pg.144    IDEMUDIA, I.M. (2007):”Right of Way and Acquisi ... Continue reading---