• Route Survey Of The Stretch Of Road From Oriawo Along Ogbomoso Road, Oyo To School Of Science, Sabo Oyo Town, Atiba Local Government Area, Oyo State

  • CHAPTER THREE -- [Total Page(s) 9]

    Page 9 of 9

    Previous   5 6 7 8 9
    • Procedure: As earlier discussed, the longitudinal section was marked out at regular interval of thirty (30) meters and the cross section at seven and half (7.5),seven and half (7.5) meters offset distance from the centre line, distance measured at each  sides were fifteen (15) metres with intermediate point at seven and half (7.5) meters.
                Leveling operation started from known control pillar (bench mark) FSS2/GPS/121 and closed on another known control pillar (bench mark) FSS2/GPS/03.
      The level observations started from a benchmark to the first nail (NL1) marked at the commencement of the route that is, where the centre line of the route started (chainage 0+000) this is also known as the first section. The level instrument was set up and leveled in-between the first nail and the benchmark, then back sighted to the staff held on benchmark (FSS2/GPS/121) as first observation after the set up, the reading was read to the staff and recorded. The instruments was turned to the staff held on C0+0000 which was the beginning of the centre line, intermediate sight was observed, then, the staff was placed at the cross section points and L1,L2,R1,R2  
      Where:
      L1=7.5m left from the centre line
      L2=15m left from the centre line
      R1=7.5m right from the centre line
      R2=15m right from the centre line
      were observed as intermediate points. After these the staffs were moved to the next section. One of the observations made to the next section would be foresight after which the instrument position would then change to backsight the same point used as the foresight then the remaining points were then observed as intermediate points on the observation made on the staff that was vertically held on those points.
      The procedure continued by making sure that the back sight was made first, followed by the intermediate sight before taken foresight readings. This method was used throughout the route leveling. All observations and measurements were taken and recorded in the field book in accordance with survey rules, regulations and departmental, project instructions.
      3.2.4.5 DETAILING
          Details along the route were fixed by Tacheometry method using Theodolite and Staff.Details within the project area that were fixed are Buildings, Roads, Wall- fence, Culvert, Streetlights, Wells, Boreholes, Electric poles,  etc.
      During the observation, the use of tacheometry and offset method were employed to effectively fix the details along the project area.Theodolite was set over station, target was set on back station (reference station) and staffs were held on details to be fixed. After bisecting and reading the horizontal circle on the target, the instrument was turned to the vertically held staff placed at the edges of the details found within the area to be fixed. The horizontal and vertical circle reading as well as upper and lower cross hair readings on each staff position were read and recorded.
                In fixing details like building,staffs was positioned at the corner of the building and in fixing details like road,staff was positioned at every change in direction of the road.   


  • CHAPTER THREE -- [Total Page(s) 9]

    Page 9 of 9

    Previous   5 6 7 8 9
    • ABSRACT - [ Total Page(s): 1 ]ABSTRACTTheproject was focused on the execution of route surveying for the purpose of road reconstruction from Oriawo along Ogbomosho road, Oyo to School of Science, Sabo Oyo Town. Stations were selected along the existing route at regular intervals as in the specificationsTheodolite traverse was run over stations, while levels were observed along the longitudinal and cross-sections of the traverse lines. All data were gathered with effective orientation from the controls, these were used to pro ... Continue reading---

         

      APPENDIX A - [ Total Page(s): 1 ]FEDERAL SCHOOL OF SURVEYING, OYO                                                                                                                                    FinalProject On Route Surveying                                                                                        ... Continue reading---

         

      LIST OF TABLES - [ Total Page(s): 1 ]LIST OF TABLESTable 3.1: Coordinates of existing ground controls used Table 3.2 Collimation test Table 3.3: Initial control check observation.  Table 3.4: Back computation of initial control used  Closing control check observation. Back computation of initial control used Table 4.1 Sample of Horizontal angle reduction Table 4.1 Back computation of traverse pegs ... Continue reading---

         

      LIST OF FIGURES - [ Total Page(s): 1 ]LIST OF FIGUREFigure 1.1: Study Area diagram    Error! Bookmark not defined.Figure 3.1 Recce Diagram Figure 3.2: Leveling instrument set up mid-way (first set-up) Figure 3.3: Leveling instrument set up( second set up) Figure 3.4 Initial control check observations  Figure 3.6 A typical monument used Figure 3.7: Longitudinal sections leveling. Figure 3.8: Cross-sectional leveling. Fig.: 3.9 – Illustration of detailing by tachometer method ... Continue reading---

         

      TABLE OF CONTENTS - [ Total Page(s): 1 ]TABLES OF CONTENTSTITLE PAGE CERTIFICATE CERTIFICATION DEDICATION  ACKNOWLEDGEMENTS ABSTRACT  LIST OF FIGURE LIST OF TABLES CHAPTER ONE 1.0 INTRODUCTION 1.1 BACKGROUND TO THE STUDY   1.2 STATEMENT OF PROBLEMS  1.3.0 AIM AND OBJECTIVES OF THE STUDY     1.3.1 AIM    1.3.2 OBJECTIVES  1.5 SCOPE OF THE PROJECT 1.6    PERSONNEL   1.7    STUDY AREA CHAPTER TWO   2.0    LITERATURE REVIEW  RECONNAISSANCE PRELIMINARY SURVEY  LOCATION SURVEY  OFFICE LOCATION: -  CHAPTER THREE ... Continue reading---

         

      CHAPTER ONE - [ Total Page(s): 3 ]CHAPTER ONE1.0 INTRODUCTION1.1 BACKGROUND TO THE STUDYEngineering Surveying is one of the branches of surveying which from the general express for any survey work carried out in connection with construction engineering and building project, it is a large scale topographical map survey which the basis for design of engineering works such as highways, railways, canals, tunnels, dams, pipelines and transmission lines.In the word of engineering and environmental studies, surveying has been recognize ... Continue reading---

         

      CHAPTER TWO - [ Total Page(s): 3 ]Traverse is a sequence of connected straight lines whose direction and distances have been measured. Traverse is also the process of connecting series of lines with known bearings and distances. It is subdivided into first order for precise measurement and second order for the establishment of secondary controls while the third order is meant for survey of tertiary and topographical features.Basak (2000) explained leveling as the art of determining the relative vertical heights of different poin ... Continue reading---

         

      CHAPTER FOUR - [ Total Page(s): 5 ]CHAPTER FOUR4.0      DATA PROCESSING AND RESULT ANALYSIS    This involved calculations that are based on acquired data from the field observation to determine locations, direction, height, distance and area etc. some specific formulae were employed for each data set depending on the desired end products and great degree of precision was required.4.1    FIELD BOOKS REDUCTIONS    Every field book was reduced to generate the final data set to be used in the final computation4.1.1   ... Continue reading---

         

      CHAPTER FIVE - [ Total Page(s): 1 ]CHAPTER FIVE5.0    SUMMARY, RECOMMENDATION AND CONCLUSION5.1     SUMMARYThe reconnaissance, which was the main planning, was carefully carried out because of its importance to good execution of any survey project or work. Having carried out the reconnaissance, six (6) second order control stations were located and used as connection along the given route. The total number of nineteen (19) stations excluding the controls where the angles and distances were determine by a closed traverse met ... Continue reading---

         

      REFRENCES - [ Total Page(s): 1 ]REFERENCESBANNISTER AND RAYMOND (1977) Surveying: 4th Ed, Pitman Publishing Ltd, London. Pg. 205BASAK, N.N (2000): Surveying and leveling, Tata Mchraw Hill publishing company Delhi, p.173, Pp.439-444.BRINKER, R. C. AND MINICK, P. R. (1987): Elementary Surveying, 6th Edition IEP- A     Donnseley New York. Pg. 3CLARK, DAVID (1972): Pane and Geodetic surveying for Engineers, 6th edition, vol.1, London: Constable and Co. Limited, pg.144    IDEMUDIA, I.M. (2007):”Right of Way and Acquisi ... Continue reading---